Read the Shoreline Stadium Case on pp. 204–205 (you can find at link above). Considering the information provided, construct a Risk Response Matrix

Read the Shoreline Stadium Case on pp. 204–205 (you can find at link above). Considering the information provided, construct a Risk Response Matrix (see text p. 220) that details at least 3 risk events that are likely for this case, your responses to the risks, contingency plans, triggers, and the responsible party for each risk event. Then, using Microsoft Project, create a Gantt chart that details the project schedule (Has been created below). Once the chart is created, answer the questions below.
1) When will the project be able to be complete? How long will it take?(will be completed 3/25/21)
2) What is the Critical Path for the project?(see critical path is below)
3) Based on the project completion date, would you recommend G&E pursue the contract? Why?

The paper is to include at least 3 peer-reviewed sources and total of 4 pages(Not including title and reference page) while including the following:

  1. Title page.
  2. Project Summary (2–3 pages), including an introduction to the project and recommendations (based on questions 1–3 from). For this assignment, include research-based rationale for your answers; be sure to include a discussion of possible risks as well as the date the project is scheduled to be completed.
  3. One-page Risk Response matrix.
  4. Reference page.

Task Name Duration Start Finish Predecessors
Baseball
clear stadium site 70 days Mon 7/3/17 Tue 10/10/17
demolish building 30 days Wed 10/11/17 Tue 11/21/17 2
set up construction site 70 days Wed 11/22/17 Tue 3/6/18 3
drive support piling 120 days Wed 3/7/18 Thu 8/23/18 4
pour lower concerete bowl 120 days Fri 8/24/18 Fri 2/15/19 5
pour main concourse 120 days Mon 2/18/19 Tue 8/6/19 6
install playing field 90 days Mon 2/18/19 Mon 6/24/19 6
construct upper steel bowl 120 days Mon 2/18/19 Tue 8/6/19 6
installs seats 140 days Wed 8/7/19 Wed 2/26/20 9
build luxury boxes 90 days Wed 8/7/19 Thu 12/12/19 9
install jumbotron 30 days Wed 8/7/19 Wed 9/18/19 9
stadium infrastructure 120 days Wed 8/7/19 Wed 1/29/20 9
construct steel canopy 75 days Thu 2/27/20 Thu 6/11/20 10
light installation 30 days Thu 2/27/20 Wed 4/8/20 10
build roof support 90 days Wed 3/7/18 Thu 7/12/18 4
construct roof 180 days Fri 7/13/18 Fri 3/29/19 16
install roof tracks 90 days Fri 6/12/20 Fri 10/16/20 14
install roof racks 90 days Mon 10/19/20 Thu 2/25/21 17,18
inspection 20 days Fri 2/26/21 Thu 3/25/21 8,11,13,15,19

Critical path:
clear stadium site
demolish building
set up construction site
drive support piling
pour lower concerete bowl
construct upper steel bowl
installs seats
construct steel canopy
Install roof tracks
Install rood racks
Inspections

Uncategorized